A reject rate that still makes sense at plant level

One line reports a ten percent reject rate at the morning meeting. Another reports one percent. What rate should the plant manager see? Averaging those percentages produces a plausible number that can send the team looking in the wrong place.

Decide what is being counted

Imagine a part that triggers two defect codes and returns to inspection after rework. Three messages in the system need not mean three inspected parts or three scrapped parts. Our unit is one uniquely identified part at its final inspection outcome. It counts as rejected if that final decision is to scrap it. The denominator contains all parts with a final decision in the same period.

Put this definition in the report. A team studying first-pass performance needs a different measure. Keep pending decisions visible as pending. Otherwise a busy shift could appear to improve quality simply because fewer of its difficult cases have received a final decision.

Why the plant gets 1.9 percent

Two lines in the same completed shift
LineInspectedRejectedRate
A1001010.0%
B90091.0%
Plant1,000191.9%
Reject rates on a common scale from 0 to 10 percent
Line A10.0%
Line B1.0%
Plant1.9%

The plant question concerns a randomly chosen inspected part. Nine times as many parts came from B, so B has nine times the weight. The simple mean of 10 and 1 gives 5.5 percent. That answers a different question about a randomly chosen line with equal weight for each line. Absolute counts tell another important story: the rates differ by a factor of ten, yet the two lines lost almost the same number of parts.

Give Power BI the right denominator

Load just the two line rows into a table named Production with numeric Inspected and Rejected columns. Leave the plant total out of the source. Define the following measure and format it as a percentage with one decimal place. Power BI recalculates both sums in the context of each row and again for the grand total.

DAX
Reject Rate =
DIVIDE(
    SUM(Production[Rejected]),
    SUM(Production[Inspected])
)

Try a day with no inspections. DIVIDE returns a blank by default when its denominator is zero. Accompany it with a message such as “No completed inspections”. A true zero rate describes a day with inspected parts and no rejects. The distinction tells the shift lead whether to check product quality or missing inspection results.

Accept the metric before publishing

Ask the process owner to run three checks. Selecting only A should give 10 out of 100. Selecting only B should give 9 out of 900. Selecting both must bring the counts to 19 and 1,000. The combined rate must lie between the two line rates. If it falls outside, inspect inconsistent date filters and joins that multiplied one side of the ratio.

Decide how to handle midnight. A part may be produced before midnight and receive its final inspection outcome afterwards. This example attributes it to the time of the final inspection. A report about a production batch might attribute it to production day instead. Document the chosen rule alongside the metric definition.

Try it yourself

The next day A inspects 20 parts and rejects 2. B inspects 180 and rejects none. What is the rate across both days? Which shortcut produces a different result?

Show the solution

The two days contain 1,200 completed inspections and 21 rejects, giving 1.75 percent. Day two alone gives 1.0 percent. Averaging the daily rates would give 1.45 percent and put the small second day on the same footing as the first.

Sources and further reading