Deutsche Bahn / Project controls

From project portfolio to milestone

Two report views connect a refurbishment project’s schedule to its outstanding deliverables.

Power BIDrillthroughGantt

Working student, data analytics · DB Fahrzeuginstandhaltung

The project team’s question

Which phase comes next, and what is still outstanding before the next quality gate? A schedule answers the first question. The second calls for a closer look at individual deliverables.

My contribution

For PEP 2.0 reporting, I built an individual project view and a synchronisation plan in Power BI. The project view compares planned and completed work across planning areas. The synchronisation plan places project phases and checkpoints on a common timeline.

Reading the report

Start with a phase or quality gate on the timeline. The project view lists the underlying deliverables, due dates and status. A broad question about progress becomes a specific item for the next project review.